Investment
Behaviour and the Cost of Project Delays
The environment
within which a transmission system operates, evolves
and grows is a result of the interaction between
the regulator and the companies that own and operate
the system. The regulatory framework is designed
to push for changes, drive down costs and allow
investment in new infrastructure or practices
that allow cost reduction or reliability over
the long term.
The financial structure of the transmission
system operator has an effect on its investment
behaviour and differs mainly according to whether
the company has a high or low proportion of debt.
Debt must be serviced from current cashflows,
while equity borrowing has to be paid from dividends
and need not be paid in certain circumstances.
The company will be likely to invest in different
projects according to this relative cashflow requirement.
For example, more highly geared companies (i.e.,
those with a high proportion of debt which must
be serviced) might be more likely to make higher
risk-higher return investments, while operators
with low debt levels are more likely to be satisfied
with lower but safer returns.
One of the issues that transmission
system operators face is how to balance potential
financial returns from a project against the costs
of delay if there are public protests against
proposed routes. The costs of delay include lost
revenues to system operators, due to transmission
capacity not being in place, and possible regulatory
penalties if delays cause transmission quality
to drop, for example if the system starts to experience
more faults due to overload.
Costs to industry and consumers
from poor quality or supply interruption can also
be significant and regulators will be interested
in minimising these costs also.
In certain circumstances, operators
can find that putting some sections of a project
underground can help to unblock local opposition,
allowing a project to proceed much sooner than
if a judicial process is used to force a 100%
overhead line approach. The savings from avoided
delays can be significantly larger than the incremental
costs of underground cables. However, transmission
system operators must be able to prove these cost
savings in making their case for investment to
the regulator.
|