Case
Study 4: Cables Enable Reinforcement of the Grid
in a Built-Up Area
When the UK's National Grid Company
needed to provide extra power into North-West
London to meet growing demand, it was not possible
to provide the transmission capacity using overhead
lines as such lines would require both extremely
large towers and a wide right-of-way along a route
that was already heavily developed. The alterative
was to install underground cable in a tunnel,
which would allow the project to run with very
little above ground disturbance.
The final design involved a 20 km
long tunnel running from Elstree in Herfordshire
to St John's Wood in North London at a depth of
around 20-30 meters below ground level - although
the maximum depth is around 80 meters in one stretch.
The tunnel has an internal diameter of 3 meters
and contains a single circuit run of 400kV XLPE
(cross-linked polyethylene) cable, the cable alone
weighing almost 2,500 tonnes. The cables are maintained
and inspected via a monorail-mounted inspection
system. To future proof the project, the tunnel
was built with capacity to hold another cable
circuit. The project included seven head house
buildings along the cable and two new transformer
substations at each end and had a budget of £200M.
The project started in March 2000 and was commissioned
in September 2005.
In addition to using modern tunnel
boring technology to offer almost no disruption
to people above the tunnel line, the project also
employed advanced monitoring and planning techniques
to ensure that there were no collisions between
the boring equipment and existing infrastructure.
Areas where care had to be taken
included Staples Corner, where road bridges on
the M1 have deep foundation pilings and existing
utility structures such as the Thames Water Ring
Main, a major sewer system and existing electricity
cables.
The project forms an important part
of the London Connection Project, which is intended
to reinforce power transmission into London. Much
of the existing 275kV infrastructure is coming
to the end of its life and is undersized for projected
demand. Progressively overlaying and replacing
the 275kV lines with 400kV lines and cables will
significantly improve capacity whilst maintaining
continuity of supply to the UK capital.
The success of this project has
prompted adoption of a similar unobtrusive tunneling
approach that will be used to install a second
400KV cable circuit in the UK between Rowdown
and Beddington in 2010.
|